The Study Process
This project is following the Environmental Assessment process for a Group ‘B’ project in accordance with the Class EA for Provincial Transportation Facilities (2000), with the opportunity for public input throughout the project.
The detail design phase of the project will focus on refinement of the design and preparation of drawings and specifications for tendering of the project for construction.
Considering that the original preliminary design was approved in 2004, the previous TESR will be reviewed to note any changes to existing environmental conditions, legislation, regulations and policies that may affect the environmental impacts and mitigation measures. This TESR Review will be incorporated into the DCRs. A significant change may require preparation of a TESR Addendum.
Public Information Centres (PICs) will be held to provide information about the refinement of the design; updated natural environmental, socio-economic, cultural and technical conditions within the study area; environmental impacts and mitigation measures to be implemented during construction; and next steps. Notices providing the time and location of the PICs will be posted on the project website. Following the PICs, digital copies of the PIC display materials will be posted on the project website.
Design and Construction Reports (DCRs) will be prepared to document the Class EA process followed, including a description of the Recommended Plan, environmental impacts and mitigation measures. DCRs will be filed for a 30-day comment period. At that time, notices will be published in a local newspaper, letters will be circulated to the study contact list and the project website will be updated to explain the review process and how the DCR can be reviewed.
In accordance with the MTO Class EA, there is no ‘bump-up’ opportunity (i.e., opportunity to make a Section 16 Order request to the Minister of Environment, Conservation and Parks) for the DCR. However, interested persons are encouraged to review and comment on the DCR. If there are no outstanding concerns after the 30-day review period has expired, further documentation will not be prepared, and construction may commence without further notice.
We Want to Hear from You!
To be added to the study contact list, please Contact Us.
If you have questions or comments for the Project Team, please Contact Us.